Awaab’s law so far

Awaab’s law was introduced following the tragic death of two-year-old Awaab Ishak in 2020. Awaab’s death was found to be linked to damp and mould in his parents’ home, leading to pressure to protect social housing tenants from hazards.

The first phase of Awaab’s law came into force on 27 October 2025. Phase 2 comes into force on 30 November 2026, and phase 3 is expected in 2027.

Requirements under phase 1

Phase 1 requires social landlords to take specific actions where emergency hazards or significant damp and mould hazards are identified.

A social landlord has a duty to:

  • investigate an emergency hazard and make it safe within 24 hours

  • carry out an investigation within ten working days from when they become aware of a significant damp and mould hazard and then make it safe within 5 working days

If the landlord cannot make the property safe from a hazard, it must provide suitable temporary accommodation free of charge.

A social landlord’s duties for emergency hazards and damp and mould remain the same under phase 2.

Find out more about phase 1 and hazards in social housing on Shelter Legal.

Extending significant hazards under phase 2

Under phase 2, the definition of significant hazard has been extended, meaning social landlords will have duties for significant hazards other than damp and mould.

From 30 November 2026, a significant hazard can include threats to health relating to:

  • electrical hazards

  • falls (including falls on the level, falls on stairs, etc, falls between levels)

  • structural collapse

  • excess cold or excess heat

  • fire and explosions

  • domestic hygiene (including personal hygiene and food safety)

What this means for tenants and landlords

Social landlords will have duties for many more problems than under phase 1, and social tenants should have more clarity on how and when a landlord must fix common safety problems.

Under phase 1 of Awaab's law, a social landlord's duties only covered emergency or damp and mould hazards. Other hazards could be dealt with through the landlord’s other repairing obligations, such as section 11 Landlord and Tenant Act 1985 or fitness for human habitation rules, but the specific requirements of Awaab's law didn't apply.

A social landlord's duties for the new significant hazards under phase 2 include the duty to:

  • carry out an investigation within ten working days of when it becomes aware of the hazard

  • make the hazard safe within five working days from when the hazard is confirmed

  • identify works to prevent the hazard and start or take steps to begin these within five working days of the investigation

If the landlord is not able to make the hazard safe in time, it must offer the tenant suitable alternative accommodation, free of charge.

Defining the new hazards

The new significant hazards are defined based on the Housing Health and Safety Rating System (HHSRS), which is used by local authorities to assess hazards in rented homes.

The government’s HHSRS guidance lists 21 different hazards, and was updated in June 2026.

Electrical hazards

A significant hazard under phase 2 includes threats to health from electrical hazards. The HHSRS guidance says electrical hazards include risks to health from ‘shock and burns resulting from exposure to electricity.’

There could be an electrical hazard due to damaged or out of date electrical fittings or appliances, exposed wires, a lack of regular inspections or testing.

Hazards from falls

A significant hazard under phase 2 might include threats to health from the risk of falls. This includes falls on stairs, between levels, on level surfaces and around baths and showers.

The HHSRS guidance says risks of falling can be exacerbated by uneven flooring, unexpected obstacles, poor lighting, low windows and windows which open widely. Some groups might be at more risk of falls, including older people, young children, and people with learning difficulties, disabilities or visual impairments.

Excess cold

A significant hazard under phase 2 could include threats to health from low indoor temperatures. The HHSRS guidance says serious health risks occur below 16C and if temperatures persist below 10C, there is an appreciable risk of hypothermia.

Vulnerable groups include those aged 65 and older. Other groups, such young children and people with pre-existing health conditions might also be at greater risk.

Excess heat

A significant hazard under phase 2 might be caused by excess heat from very high indoor temperatures. Excess heat can lead to hyperthermia, heat exhaustion, heat stroke and dehydration.

There are no specific temperatures defined in the government’s HHSRS guidance for when excess heat might become a hazard. Government guidance states those over 65 and over are a vulnerable group. Other groups such as very young children, people with pre-existing health conditions and people on certain medications might also be at greater risk.

Domestic hygiene (including personal hygiene and food safety)

A significant hazard under phase 2 might include threats to health from:

  • poor design, layout and construction so a property cannot be easily kept clean and hygienic

  • access and space for pests

It also includes threats to health from inadequate facilities for:

  • managing household waste

  • storage, preparation and cooking of food

  • personal washing and clothes washing facilities

  • sanitation and drainage

A threat to health includes potential threats to mental health from the impact of any of these issues.

Structural collapse

A significant hazard under phase 2 might include threats to health from structural collapse. This includes the threat of collapse of all or part of a property including falling elements.

Fire and explosions

A significant hazard under phase 2 can include threats to health from exposure to fire, smoke and fumes. It also includes any potential threats to health from explosions, heat, or the structural collapse because of a fire or explosion.

Excluded fire hazards

Some specific fire hazards are excluded from Awaab’s law under phase 2. This includes hazards relating to fire in the common parts where there are two or more homes in one building, such as blocks of flats, houses in multiple occupation (HMOs) and student halls.

Fire hazards in the common parts of these buildings are already covered by the Regulatory Reform (Fire Safety) Order 2002. The government says it does not want to duplicate existing rules.

Change to the scope of significant hazards

Phase 2 changes the definition of a significant risk of harm under Awaab's law. This definition affects when something is considered a significant hazard and therefore whether it is in scope.

Under phase 1, the definition of a significant risk of harm is:

‘a risk of harm to the occupier’s health or safety that a reasonable landlord would take steps to make safe as a matter of urgency (but not within 24 hours)’

From 30 November, as part of phase 2, this changes to:

‘a risk of harm to the occupier’s health or safety that a reasonable landlord would take steps to make safe within 15 working days (but not within 24 hours)’

What this might mean

Government guidance on phase 2 says that in some cases, where a reasonable landlord cannot make the hazard safe within 15 days, an issue might fall out of scope of Awaab’s law. For example, if the work to make safe requires large-scale structural work.

The guidance is clear that issues out of scope for this reason still need to be addressed under other duties, such as section 11 or fitness for human habitation. But if a problem is out of scope for Awaab’s law, the landlord is not required to meet the strict timelines to make safe or to provide suitable alternative accommodation. This could mean it’s more difficult for tenants to get disrepair and safety issues resolved where larger work is needed.

The government says the change intends to clarify the language used in phase 1, which made it difficult to clearly distinguish between an emergency and significant hazard.

How Awaab’s law is working so far

A year on from the implementation of phase 1, how is it working in practice?

There have been some concerns raised about whether Awaab's law has been working as planned. The Housing Ombudsman Service identified some initial problems in a June 2026 report, including ‘incomplete risk assessments, unexplained delays, unevidenced reports of no access and no consideration of temporary moves.’

The importance of record-keeping

In particular, the Ombudsman highlight concerns about landlord record-keeping. 'Knowledge and information management is often the foundation to an effective complaint response. Having good accurate records means landlords can evidence where they have acted and assess whether escalations may be required.'

Under Awaab’s law landlords are required to issue a summary to the tenant of their investigations, but if there is no clear record of the landlord’s assessments of a hazard, this can affect the tenant’s ability to challenge the landlord on specific details.

The need for effective triage

The Housing Ombudsman Service say 'it can be difficult to identify what is an emergency or a significant hazard, especially based on an initial report. This highlights the importance of robust triage processes.' If a hazard is not triaged properly, or changes in circumstances are missed, a social landlord might not identify when it has duty to take emergency action.

The government has issued additional guidance for phase 2 to assist social landlords in triaging hazards.

Read the government guidance: Awaab’s Law Phase 2: Guidance to support triaging of hazards - GOV.UK

What’s next

The phased implementation of Awaab's law is due to continue in 2027, when phase 3 will extend the rules to all HHSRS hazards in social housing, aside from overcrowding. But as with phase 1 and 2, the impact depends on proper implementation of the rules by social landlords.

It's also important that social landlords don't just stop at their Awaab's law duties, the Housing Ombudsman say. 'While Awaab's law is crucial, the duties are still reactive. Social landlords should be seeking to prevent harm, for example, using data and technology to prompt proactive repairs and maintenance before hazards can arise.'

Private rented sector

The government is currently consulting on extending Awaab’s law to the private rented sector, but this is not expected to be introduced for several years. The exact requirements might differ from the social rented sector rules.

About the author

Madeleine Hunter is a senior legal content producer and former housing adviser at Shelter.

Step 1 of 3
How helpful was this page?Select an option from 1 - Not helpful at all to 5 - Very helpful, with 1 - Not helpful at all being Not helpful at all and 5 - Very helpful being Very helpful